Coastal Rail Emergency Projects
Coastal Rail Emergency Project – Area 3
Project Details
The Coastal Rail Emergency Project – Area 3 is constructing a 1,400-foot-long catchment wall on the bluff side of the tracks at Mariposa Point. The wall will extend from the El Portal Beach access point to Linda Lane. The San Clemente Pedestrian Beach Trail will also be restored as part of this project.
Construction work hours are Monday through Saturday from 7 a.m. to 10 p.m.
The schedule is subject to change due to inclement weather or unforeseen operational issues.
Construction Updates
Construction Activities
Crews have completed installation of the wood lagging panels for the catchment wall and are continuing with drainage work and shotcrete operations. Construction of the verdura wall to support the new San Clemente Beach Trail is also underway and expected to continue through May.
In the coming weeks, crews are expected to begin work on the access bridge at Mariposa Channel. Activities are anticipated to begin mid-April and include removal of the current bridge and grading.
Daytime intermittent deliveries via truck through North Beach and Linda Lane are expected to take place as needed to support these activities.

San Clemente Beach Trail
The San Clemente Beach Trail will be closed from the North Beach parking lot to El Portal during work hours but will reopen at the end of each workday and will be open on Sundays. The trail will be closed from El Portal to Linda Lane until project completion.
As part of the Coastal Rail Emergency Project, the San Clemente Beach Trail is being restored and is expected to reopen to the public upon project completion in Summer 2026. For additional information about the trail improvements and project features, check out our Trail Benefits Flyer.

Rendering of San Clemente Beach Trail
Beach Access
The Mariposa underpass is closed. Beach access at Dije Court and El Portal are temporarily closed to ensure the safety of the public. The public can still access the beach using the El Portal beach underpass and the Linda Lane beach underpass.
View our interactive map for current beach access closures and detour routes.
Staging Areas
Contractors are staging equipment and materials in the North Beach parking lot and on a city-owned vacant lot at the corner of Avenida Estacion and Calle Deshecha. Several parking spaces along Linda Lane will also be utilized for construction vehicle parking on a first-come, first-served basis.


Stay Connected
To receive weekly email communications about the project, sign up here.
Construction Notices
- January 30, 2026
- January 23, 2026
- January 16, 2026
- January 9, 2026
- January 2, 2026
- December 19, 2025
- December 12, 2025
- December 8, 2025
- December 5, 2025
- November 21, 2025
- November 14, 2025
- November 7, 2025
- October 31, 2025
- October 24, 2025
- October 17, 2025
- October 10, 2025
- October 3, 2025
- September 26, 2025
- September 19, 2025
- Special Alert - September 12, 2025
- September 12, 2025
- September 5, 2025
- May 29, 2025
- May 22, 2025
- May 16, 2025
- May 8, 2025
- May 1, 2025
- April 25, 2025
Photo Gallery
Aerial view of the catchment wall 4/10/26
Construction of the verdura wall 4/10/26
Catchment Wall Progress 4/3/26
Wood lagging installation 4/3/26
Catchment Wall 3/27/26
Steel beam installation 3/27/26
Catchment Wall 3/20/26
Slope excavation and drainage installation 3/20/26
Catchment Wall 3/13/26
Utility and Drainage Connection 3/16/26
Catchment Wall 3/6/26
Excavation and Pile Installation 3/6/26
Catchment Wall
Excavation and Beam Installation
Catchment Wall
Fence Installation
Catchment Wall
Steel Beam and Rebar Installation
Catchment Wall
Steel Beam and Rebar
Shoring and catchment wall
Pile Installation activity
Drill rig and steel beams
Steel beams installed for the catchment wall
Rebar cages delivered to the project site
Drilling operations
Rebar cages
Installing steel piles
Drilling operations