Coastal Rail Emergency Projects
Coastal Rail Emergency Project – Area 3
Project Details
The Coastal Rail Emergency Project – Area 3 is constructing a 1,400-foot-long catchment wall on the bluff side of the tracks at Mariposa Point. The wall will extend from the El Portal Beach access point to Linda Lane. The San Clemente Pedestrian Beach Trail will also be restored as part of this project.
Construction work hours are Monday through Saturday from 6 a.m. to 10 p.m.
The schedule is subject to change due to inclement weather or unforeseen operational issues.
Construction Update
Crews reached another milestone on the 1,400-foot permanent catchment wall with the completion of shotcrete activities. This operation applied concrete to the wall in two layers: a base layer that formed the structure and a second layer that provided the textured finish.
Following the shotcrete activities, crews are expected to paint the wall to blend in with the area’s natural landscape.
In the coming weeks, crews will continue on the Verdura wall, and access bridge at the Mariposa Channel, which includes work on abutment footings, walls, and stairs.
Additionally, work hours will return to Monday through Saturday, 6 a.m. to 6 p.m. Some intermittent night work may be needed for future activities.
This work may be loud. The schedule is subject to change due to inclement weather or unforeseen operational issues.

San Clemente Beach Trail
The San Clemente Beach Trail will be closed from the North Beach parking lot to El Portal during work hours but will reopen at the end of each workday and will be open on Sundays. The trail will be closed from El Portal to Linda Lane until project completion.
As part of the Coastal Rail Emergency Project, the San Clemente Beach Trail is being restored and is expected to reopen to the public upon project completion in Summer 2026. For additional information about the trail improvements and project features, check out our Trail Benefits Flyer.

Rendering of San Clemente Beach Trail
Beach Access
The Mariposa underpass is closed. Beach access at Dije Court and El Portal are temporarily closed to ensure the safety of the public. The public can still access the beach using the El Portal beach underpass and the Linda Lane beach underpass.
View our interactive map for current beach access closures and detour routes.
Staging Areas
Contractors are staging equipment and materials in the North Beach parking lot and on a city-owned vacant lot at the corner of Avenida Estacion and Calle Deshecha.


Stay Connected
To receive weekly email communications about the project, sign up here.
Construction Notices
- May 22, 2026
- May 15, 2026
- May 8, 2026
- May 1, 2026
- April 24, 2026
- April 17, 2026
- April 10, 2026
- April 3, 2026
- March 27, 2026
- March 20, 2026
- March 13, 2026
- March 6, 2026
- February 27, 2026
- February 20, 2026
- February 19, 2026
- February 13, 2026
- February 6, 2026
- January 30, 2026
- January 23, 2026
- January 16, 2026
- January 9, 2026
- January 2, 2026
- December 19, 2025
- December 12, 2025
- December 8, 2025
- December 5, 2025
- November 21, 2025
- November 14, 2025
- November 7, 2025
- October 31, 2025
- October 24, 2025
- October 17, 2025
- October 10, 2025
- October 3, 2025
- September 26, 2025
- September 19, 2025
- Special Alert - September 12, 2025
- September 12, 2025
- September 5, 2025
- May 29, 2025
- May 22, 2025
- May 16, 2025
- May 8, 2025
- May 1, 2025
- April 25, 2025
Photo Gallery
Aerial views of completed structural shotcrete for catchment wall 6/12/26
Aerial views of completed structural shotcrete for catchment wall 6/12/26
Crews working on bridge construction activities 6/12/26
Aerial view of work activities at the Mariposa channel 6/4/26
Crews working on bridge construction activities 6/4/26
Aerial view of Mariposa bridge construction activities 5/29/26
Crews working on the bridge at the Mariposa Channel 5/29/26
Aerial view of Mariposa bridge construction activities 5/22/26
Crews performing excavation operations 5/22/26
Catchment wall shotcrete placement activities 5/15/26
Crews performing drilling operations on Mariposa bridge 5/15/26
Catchment wall shotcrete placement activities 5/11/26
Crews performing rebar installation work 5/11/26
Catchment wall lagging and verdura wall construction activities 5/1/26
Crews performing utility work 5/1/26
Catchment wall wood lagging installation 4/24/26
Verdura wall construction activities 4/24/26
Verdura wall construction activities 4/17/26
Aerial view of the catchment wall 4/10/26
Construction of the verdura wall 4/10/26
Catchment Wall Progress 4/3/26
Wood lagging installation 4/3/26
Catchment Wall 3/27/26
Steel beam installation 3/27/26
Catchment Wall 3/20/26
Slope excavation and drainage installation 3/20/26
Catchment Wall 3/13/26
Utility and Drainage Connection 3/16/26
Catchment Wall 3/6/26
Excavation and Pile Installation 3/6/26
Catchment Wall
Excavation and Beam Installation
Catchment Wall
Fence Installation
Catchment Wall
Steel Beam and Rebar Installation
Catchment Wall
Steel Beam and Rebar
Shoring and catchment wall
Pile Installation activity
Drill rig and steel beams
Steel beams installed for the catchment wall
Rebar cages delivered to the project site
Drilling operations
Rebar cages
Installing steel piles
Drilling operations