Transit Facility Projects
                        We’re planning a robust, environmentally friendly and energy-efficient transit future with a new Transit Security and Operations Center, electric charging stations for zero emission buses and new generators for 24/7 bus operations.
                    
         
        Project
                        
                        Status
                    
                                The planned Transit Security and Operations Center (TSOC) will generally house some of Annex functions, provide adequate spaces for these functions, improve efficiency of room layouts, and provide space for future functions and/or expansion.
                                
                        In Progress
                            
                            In Progress
                        
                    
                                Electric vehicle charging stations will be placed at OCTA’s Garden Grove and Santa Ana bus bases to support 30 electric operator relief vehicles and five employee vehicles at each base. 
                                
                        Completed
                            
                            Completed
                        
                    
                                Standby power generators will be placed at OCTA’s Anaheim and Irvine Construction Circle bus bases to support 24/7 operations in the event of a utility power loss. 
                                
                        Completed
                            
                            Completed