Skip to main content

San Juan Creek Bridge Replacement Project

Construction Updates

The Orange County Transportation Authority (OCTA), in coordination with Metrolink, is replacing the railroad bridge over San Juan Creek. Built in 1917, the bridge has reached the end of its useful life and will be replaced by a new three-span girder bridge.

Project Details

SJC Bridge

The San Juan Creek Bridge Replacement Project will replace the railroad bridge over San Juan Creek in the City of San Juan Capistrano.

The project will construct a new three-span girder bridge west of the existing bridge. The new bridge will enhance safety, reduce maintenance needs, and meet current design and bridge load standards. The existing bridge will be demolished, and a new foundation and substructure will be installed for a potential future bridge. There are no plans to construct a second bridge but if a need arises, the supporting infrastructure will be in place.

The bridge serves Metrolink and Amtrak Pacific Surfliner passenger trains, as well as freight trains.

The project will also:

  •    Construct tracks
  •    Construct a new bikeway underpass
  •    Construct retaining walls
  •    Install new utilities and signals
  •    Remove vegetation

Construction Activities


Nighttime Utility Work Extended through September

Nighttime utility work is now expected to continue into September as crews continue to perform underground utility work related to the relocation of communication and signal lines.

The adjacent communities may experience noise and lighting from the operation. Train horns may also sound because the Federal Railroad Administration (FRA) guidelines require that all trains sound their horns when workers are present on or around railroad tracks. This federal mandate applies to construction zones.

Channel Demobilization

Crews are now expected to begin demobilization efforts from the San Juan Creek after Labor Day weekend. This will require all materials and equipment to be moved out and the channel restored to its original condition before mid-September.

Work outside of the channel will be ongoing until the next dry season in Spring 2026. These activities include continued work on the new railroad bridge such as installing asphalt planks and handrails for the bikeway underpass. Track work such as welding track ties and installing ballast will continue along with the construction on several retaining walls.

Labor Day Holiday Construction Schedule

In observance of Labor Day, there will be no construction activities scheduled Monday, Sept. 1. Crews will resume work on Tuesday, Sept. 2.

This work may be loud. This schedule is subject to change due to inclement weather or unforeseen operational issues.



Community Impacts


Train Horns

Federal Railroad Administration (FRA) guidelines require all trains to sound their horns when workers are present, in emergency situations or when there are trespassers on or around railroad tracks. This federal mandate applies to construction zones. As a result, for the safety of construction workers, train crews and passengers, and the public, horns will be sounded when trains pass through the area.

Additional Impacts

The public and businesses adjacent to the work area may experience noise and vibration from demolition and drilling activities as well as light from construction operations. Noise may also be generated from construction equipment back-up alarm. The alarms are required by state regulation.

Community Outreach

The Public Outreach team regularly hosts project information booths at Descanso Park in San Juan Capistrano. In addition, the team participates in community events.

Businesses or civic organizations that would like to receive a project presentation may email the team at SJCBridge@octa.net.

Latest Activity

Document Icon
PDF
PDF
August 29, 2025
Document Icon
PDF
PDF
August 15, 2025
Document Icon
PDF
PDF
August 7, 2025
Document Icon
PDF
PDF
August 1, 2025
Document Icon
PDF
PDF
July 25, 2025
Document Icon
PDF
PDF
July 18, 2025
Document Icon
PDF
PDF
July 11, 2025
Document Icon
PDF
PDF
July 2, 2025
Document Icon
PDF
PDF
June 20, 2025
Document Icon
PDF
PDF
June 13, 2025
Document Icon
PDF
PDF
June 6, 2025
Document Icon
PDF
PDF
May 30, 2025
Document Icon
PDF
PDF
May 23, 2025
Document Icon
PDF
PDF
May 16, 2025
Document Icon
PDF
PDF
May 9, 2025
Document Icon
PDF
PDF
May 2, 2025

Contact the Outreach Team

If you have any questions or would like to request information in another language, please contact the Outreach Team at (800) 724-0353 or email SJCBridge@octa.net.