Skip to main content

San Juan Creek Bridge Replacement Project

Construction Updates

The Orange County Transportation Authority (OCTA), in coordination with Metrolink, is replacing the railroad bridge over San Juan Creek. Built in 1917, the bridge has reached the end of its useful life and will be replaced by a new three-span girder bridge.

Project Details

SJC Bridge

The San Juan Creek Bridge Replacement Project is replacing the railroad bridge over San Juan Creek in the City of San Juan Capistrano.

The project is constructing a new three-span girder bridge west of the existing bridge. The new bridge will enhance safety, reduce maintenance needs, and meet current design and bridge load standards. The existing bridge will be demolished, and a new foundation and substructure will be installed for a potential future bridge. There are no plans to construct a second bridge but if a need arises, the supporting infrastructure will be in place.

The bridge serves Metrolink and Amtrak Pacific Surfliner passenger trains, as well as freight trains.

The project will also:

  •    Construct tracks
  •    Construct a new bikeway underpass
  •    Construct retaining walls
  •    Install new utilities and signals
  •    Remove vegetation

Sheet Pile Installation Continues in San Juan Creek

Crews are continuing to install steel beams, also known as sheet piles, within San Juan Creek. Work within the creek is expected to continue until the end of the dry season in mid-September.

This work may generate noise and vibration for the surrounding community. No road or trail closures are anticipated.

Work hours are Monday through Saturday, from 6 a.m. to 6 p.m. Weekend work is expected to continue through mid-September to maintain progress within the creek.

The surrounding community may experience intermittent construction noise and vibration during sheet pile installation. No road or trail closures are anticipated. This work may be loud. The schedule is subject to change due to inclement weather or unforeseen operational issues

Pile Installation

Construction Update

Work on the bridge foundation progresses within San Juan Creek with the construction of the foundation caps.

Remaining work on the foundation includes installing reinforcing steel, pouring concrete, and restoring the creek slope.

Sheet pile deliveries and construction equipment will continue to access the work area via Camino Capistrano and exit via Stonehill Drive. Water trucks will continue to be deployed along the haul route to help mitigate dust.

This work may be loud. The schedule is subject to change due to inclement weather or unforeseen operational issues.

Latest Activity



Yellow alert within a circle
PDF
PDF
August 21, 2026
Yellow alert within a circle
PDF
PDF
August 14, 2026
Yellow alert within a circle
PDF
PDF
August 7, 2026
Yellow alert within a circle
PDF
PDF
July 31, 2026

Contact the Outreach Team

If you have any questions or would like to request information in another language, please contact the Outreach Team at (800) 724-0353 or email SJCBridge@octa.net.