Construction Activities
Retaining Wall Update
Construction continues on four retaining walls around San Juan Creek Trail that are needed to support the new railroad bridge. This operation required a series of drilling and concrete pours to install steel beams, also referred to as piles, which was completed in January. Crews have begun installing concrete panels that will be placed between the piles and will continue this work through March.
All four walls are expected to be completed in late 2025.

Retaining wall panels being delivered to the construction site.

Crews installing retaining wall panels.
Community Impacts
San Juan Creek Trail Intermittent Closures
A segment of the San Juan Creek Trail will be closed intermittently beginning as soon as Monday, March 24 and continuing through Tuesday, April 1 to allow crews to continue constructing retaining walls adjacent to the trail. To accommodate this activity, pedestrians and bicyclists will be briefly stopped by flaggers until the trail is clear.
This work may be loud. Schedule is subject to change due to inclement weather or unforeseen operational issues.
Train Horns
Federal Railroad Administration (FRA) guidelines require all trains to sound their horns when workers are present, in emergency situations or when there are trespassers on or around railroad tracks. This federal mandate applies to construction zones. As a result, for the safety of construction workers, train crews and passengers, and the public, horns will be sounded when trains pass through the area.
Additional Impacts
The public and businesses adjacent to the work area may experience noise and vibration from demolition and drilling activities as well as light from construction operations. Noise may also be generated from construction equipment back-up alarms. The alarms are required by state regulation.