I-5 (I-405 to SR-55) Improvement Project
Construction Updates
Ensure you have the latest information on construction activities and project milestones delivered directly to your inbox. Use the Stay Informed form to subscribe to our project notifications, which will begin once construction is underway. If you require further assistance, please contact our community outreach team—we are ready to assist you.
Click to download to view and print a detailed list of closures and detours.

Technology Drive Bridge Work

Nighttime construction activities and closures are expected at the Technology Drive/I-5 and SR-133 bridges for electrical work. This work requires full road closures of westbound (WB) Technology at I-5 and SR-133.
Anticipated Schedule
Monday night, Nov. 16 through Friday night, Nov. 20.
Anticipated Work Hours
As early as 9 p.m. to 5 a.m.
Jamboree Road Bridge Work

Nighttime construction activities and closures are expected at the Jamboree Road/I-5 bridge to remove the Jamboree median barrier and to restripe. This work requires full road closures of eastbound (EB) and WB Jamboree at I-5. Crews are expected to alternate work and closures between both sides of Jamboree.
Anticipated Schedule
Wednesday night, Nov. 18 through Friday night, Nov. 20.
(Only one night of work is anticipated during this period, weather permitting.)
LANES REOPENING! The long-term lane closures closest to the median in both directions of Jamboree are expected to reopen as early as Friday, Nov. 20 or during the week of Nov. 23, ahead of the Thanksgiving holiday!
Anticipated Work Hours
As early as 10 p.m. to 5 a.m.
Construction Closures & Detours
View the latest project closures and detours using the interactive map below.
Social Media Feed
Latest Activity
- As of Oct. 9, 2026
- Sand Canyon Pile Installation Alert
As of Oct. 8, 2026 - As of Oct. 2, 2026
- As of Sept. 25, 2026
- Peters Canyon Drainage Demolition Alert
As of Sept. 22, 2026 - As of Sept. 21, 2026
- As of Sept. 18, 2026
- As of Sept. 14, 2026
- As of Sept. 11, 2026
- As of Sept. 4, 2026
- As of Aug. 28, 2026
- As of Aug. 26, 2026
- As of Aug. 21, 2026
- As of Aug. 19, 2026
- As of Aug. 14, 2026
- As of Aug. 7, 2026
- As of July 31, 2026
- As of July 24, 2026
- As of July 20, 2026
- As of July 17, 2026
- As of July 13, 2026
- As of July 10, 2026
- As of July 7, 2026
- As of July 2, 2026
- As of June 26, 2026
- As of June 22, 2026
- As of June 19, 2026
- As of June 12, 2026
- As of June 5, 2026
- As of June 2, 2026
- As of May 29, 2026
- As of May 22, 2026
- As of May 15, 2026
- As of May 8, 2026
- As of May 1, 2026
- As of April 24, 2026
- As of April 17, 2026
- As of April 10, 2026
- As of April 3, 2026
- As of April 1, 2026
- As of March 27, 2026
- As of March 20, 2026
- As of March 13, 2026
- As of Feb. 27, 2026
- As of Feb. 13, 2026
- As of Feb. 10, 2026
Photo Gallery
Crews performing drilled foundation work to support the I-5 bridge construction.
Crews are assembling reinforcing steel cages for bridge foundation construction beneath the I-5 bridge
Aerial photos of project area
Aerial photos of project area
I-5/Peters Canyon Hiking & Riding Trail
Jamboree and SR-261 Bridges at I-5
Segment 1
Segment 2





