I-5 (I-405 to SR-55) Improvement Project
Construction Updates
Ensure you have the latest information on construction activities and project milestones delivered directly to your inbox. Use the Stay Informed form to subscribe to our project notifications, which will begin once construction is underway. If you require further assistance, please contact our community outreach team—we are ready to assist you.
Click to download to view and print a detailed list of closures and detours.

Sand Canyon Pile Installation
Crews are expected to perform nighttime pile driving at the Sand Canyon Avenue/I-5 Bridge. This work must take place at night to safely accommodate large equipment and reduce daytime tra¬ffic impacts.
What to Expect
Noise: Pile driving will generate loud noise and repetitive hammering sounds.
Vibration: Nearby properties may experience temporary ground vibrations.
Crews will mobilize equipment and begin closures as early as 10 p.m. Tuesday, Oct. 13 and drive piles from approximately 12 a.m. to 5 a.m. Wednesday, Oct. 14.
This work will require ramp, lane and connector closures. For additional information regarding closures and detours, view the interactive map below.
This work may be loud. The schedule is subject to change due to inclement weather or unforeseen operational issues.
Peters Canyon CIDH Work
Daytime construction activities will continue at the I-5 Peters Canyon Hiking and Riding Trail Bridge for cast-in-drilled-hole (CIDH) work.
Intermittent full closures of the Peters Canyon Hiking and Riding Trail at I-5 may occur through late 2026 for moving equipment in the construction area.
At least one lane in each direction will remain open at all times, unless otherwise noted.
Anticipated Schedule
CIDH Work: Ongoing through mid-October.
Anticipated Work Hours
Daytime: As early as 6 a.m. to 4 p.m.
Nighttime: As early as 9 p.m. to 5 a.m.
Construction Closures & Detours
View the latest project closures and detours using the interactive map below.
Social Media Feed
Latest Activity
- As of Sept. 18, 2026
- As of Sept. 14, 2026
- As of Sept. 11, 2026
- As of Sept. 4, 2026
- As of Aug. 28, 2026
- As of Aug. 26, 2026
- As of Aug. 21, 2026
- As of Aug. 19, 2026
- As of Aug. 14, 2026
- As of Aug. 7, 2026
- As of July 31, 2026
- As of July 24, 2026
- As of July 20, 2026
- As of July 17, 2026
- As of July 13, 2026
- As of July 10, 2026
- As of July 7, 2026
- As of July 2, 2026
- As of June 26, 2026
- As of June 22, 2026
- As of June 19, 2026
- As of June 12, 2026
- As of June 5, 2026
- As of June 2, 2026
- As of May 29, 2026
- As of May 22, 2026
- As of May 15, 2026
- As of May 8, 2026
- As of May 1, 2026
- As of April 24, 2026
- As of April 17, 2026
- As of April 10, 2026
- As of April 3, 2026
- As of April 1, 2026
- As of March 27, 2026
- As of March 20, 2026
- As of March 13, 2026
- As of Feb. 27, 2026
- As of Feb. 13, 2026
- As of Feb. 10, 2026
Photo Gallery
Crews performing drilled foundation work to support the I-5 bridge construction.
Crews are assembling reinforcing steel cages for bridge foundation construction beneath the I-5 bridge
Aerial photos of project area
Aerial photos of project area
I-5/Peters Canyon Hiking & Riding Trail
Jamboree and SR-261 Bridges at I-5
Segment 1
Segment 2





