I-5 (I-405 to SR-55) Improvement Project
Construction Updates
Ensure you have the latest information on construction activities and project milestones delivered directly to your inbox. Use the Stay Informed form to subscribe to our project notifications, which will begin once construction is underway. If you require further assistance, please contact our community outreach team—we are ready to assist you.
Click to download to view and print a detailed list of closures and detours.

NB Overhead Sign Removal

Construction activities are expected to remove overhead signage on northbound (NB) I-5. This work requires nightly full closures of NB I-5 between Alton Parkway and SR-133 and the southbound (SB) I-5 carpool (HOV) lane adjacent to the center median. Nightly closures are scheduled as early as 10 p.m. to 5 a.m. Thursday, Aug. 20 and Friday, Aug. 21. NB lane closures start as early as 9 p.m. followed by the full closure at 10 p.m.
This work may be loud. The schedule is subject to change due to inclement weather or unforeseen operational issues.
Peters Canyon Demolition

Nighttime construction activities and closures are coming up for the demolition of the remaining outer portions of I-5 at the Peter Canyon Hiking & Riding Trail. This work requires full closures of westbound (WB) and eastbound (EB) Peters Canyon Trail between Bryan Avenue and Harvard Avenue/Walnut Avenue.
Daytime construction activities are ongoing at the I-5 Peters Canyon Hiking and Riding Trail Bridge for cast-in-drilled-hole (CIDH) work.
Intermittent full closures of the Peters Canyon Hiking and Riding Trail at I-5 may occur through late 2026 for moving equipment in the construction area.
At least one lane in each direction will remain open at all times, unless otherwise noted.
Anticipated Schedule
Demolition: As early as Monday, Aug. 24 through Saturday, Aug. 29, 2026.
CIDH: Ongoing through late 2026.
Anticipated Work Hours
Daytime: As early as 6 a.m. to 4 p.m.
Nighttime: As early as 9 p.m. to 5 a.m.
Construction Closures & Detours
View the latest project closures and detours using the interactive map below.
Social Media Feed
Latest Activity
- As of July 17, 2026
- As of July 13, 2026
- As of July 10, 2026
- As of July 7, 2026
- As of July 2, 2026
- As of June 26, 2026
- As of June 22, 2026
- As of June 19, 2026
- As of June 12, 2026
- As of June 5, 2026
- As of June 2, 2026
- As of May 29, 2026
- As of May 22, 2026
- As of May 15, 2026
- As of May 8, 2026
- As of May 1, 2026
- As of April 24, 2026
- As of April 17, 2026
- As of April 10, 2026
- As of April 3, 2026
- As of April 1, 2026
- As of March 27, 2026
- As of March 20, 2026
- As of March 13, 2026
- As of Feb. 27, 2026
- As of Feb. 13, 2026
- As of Feb. 10, 2026
Photo Gallery
Crews performing drilled foundation work to support the I-5 bridge construction.
Crews are assembling reinforcing steel cages for bridge foundation construction beneath the I-5 bridge
Aerial photos of project area
Aerial photos of project area
I-5/Peters Canyon Hiking & Riding Trail
Jamboree and SR-261 Bridges at I-5
Segment 1
Segment 2





