SR-91 (SR-57 to SR-55) Improvement Project
Construction Updates
Directional Freeway Closures for Girder Installation
WHAT: In preparation for bridge construction, crews are anticipated to install girders, which will require nighttime directional freeway closures. Girder installation involves the use of cranes to lift and place large beams into position. To safely accommodate this work, the following closures will be in place.
WHEN:
- 11 p.m. to 7 a.m., Friday, March 6 and Saturday, March 7 (into Sunday morning)
- 11 p.m. to 7 a.m., Friday, March 13 and Saturday, March 14 (into Sunday morning)
CLOSURES:
Friday, March 6 and Saturday, March 7 (into Sunday morning):
- Eastbound SR-91 from Lakeview Avenue to Imperial Highway
- Eastbound and Westbound 91 Express Lanes
- Northbound Lakeview Avenue
- Eastbound SR-91 Lakeview on-ramp

Friday, March 13 and Saturday March,14 (into Sunday morning):
- Westbound SR-91 from Lakeview Avenue to Tustin Avenue
- Eastbound and Westbound 91 Express Lanes
- Northbound Lakeview Avenue
- Eastbound SR-91 Lakeview on-ramp

These closures are necessary to safely accommodate crane operations and girder placement activities.
Potential impacts may include backup alarms from construction vehicles, bright lights, noise, and traffic delays. This work may be loud. The schedule is subject to change due to inclement weather or unforeseen operational issues.
Changes to Westbound SR-91 On-Ramp at Lakeview Avenue
As of Monday, March 2, motorists traveling both NB and SB on Lakeview Avenue will use a new signalized intersection to access the newly realigned WB SR-91 straight on-ramp, and the WB SR-91 loop on-ramp at Lakeview Avenue will be permanently closed.
Additionally, the eastern side of Lakeview Avenue will be fully closed to pedestrians through August 2026. The western side will be accessible to pedestrians.
As of July 7, 2025, Eastbound SR-91 Loop On-Ramp is Closed for Approximately Two Years

Construction on Segment 2 of the SR-91 Improvement Project is expected to begin in mid-2026.
Segment 3 Construction Coming Soon
Construction on Segment 3 of the SR-91 Improvement Project is expected to begin in February 2026, bringing major upgrades to the SR-91/SR-57 interchange and surrounding areas to improve traffic flow, enhance safety, and support long-term mobility.
During the week of March 2, crews are scheduled to continue putting up construction signs within the corridor. K-rail placement and clearing and grubbing activities will follow.
Additional schedule updates will be shared in upcoming alerts.
Closures and Detours

A key element of this work is the full reconstruction of the La Palma Avenue bridge, which will provide modern lanes, wider sidewalks, and improved shoulders for drivers, pedestrians, and cyclists. To complete this effort, the existing bridge will first be demolished during two weekends of 55-hour directional closures on SR-91, followed by a year-long closure of the bridge itself to allow for reconstruction.
Stay informed with updates
Sign up for our construction alerts, which will be sent regularly when construction starts, by filling out the Stay Informed form. If you have further questions, please feel free to contact our team and we will be happy to help. Previous weekly construction alerts are posted at the bottom of this page.
NEW! You can now sign up to receive important construction notifications. Text SR91PROJECT to 877-676-4182 to subscribe.
Construction Closures & Detours
Closures and detours for the SR-91 Improvement Project
Social Media Feed
Latest Activity
- As of Feb. 20, 2026
- As of Feb. 13, 2026
- As of Feb. 6, 2026
- As of Jan. 30, 2026
- As of Jan. 23, 2026
- As of Jan. 16, 2026
- As of Jan. 9, 2026
- As of Jan. 5, 2026
- As of Dec. 22, 2025
- As of Dec. 12, 2025
- As of Dec. 5, 2025
- As of Nov. 21, 2025
- As of Nov. 14, 2025
- As of Nov. 3, 2025
- As of Oct. 31, 2025
- As of Oct. 24, 2025
- As of Oct. 17, 2025
- As of Oct. 13, 2025
- As of Oct. 3, 2025
- As of Sep. 29, 2025
- As of Sep. 22, 2025
- As of Sep. 15, 2025
- As of Sep. 8, 2025
- As of Aug. 29, 2025
- As of Aug. 22, 2025
- As of Aug. 15, 2025
- As of Aug. 8, 2025
- As of August 4, 2025
- As of July 25, 2025
- As of July 18, 2025
- As of July 11, 2025
- As of July 3, 2025
- As of June 27, 2025
- As of June 20, 2025
- As of June 13, 2025
- As of June 6, 2025
- Week May 30, 2025
- Week May 23, 2025
- Week May 16, 2025
- Week of May 9, 2025
- Week of May 2, 2025
- Week of April 25, 2025
- Week of April 21, 2025
- Week of April 14, 2025
Contact the SR-91 Community Outreach Team
If you have questions or would like to request information in other language, please contact the Outreach Team at (888) 280-7966 or email 91project@octa.net.
Text SR91PROJECT to 877-676-4182 to receive text alerts.



