ORANGE – The Orange County Transportation Authority Board of Directors on Monday authorized emergency actions to stabilize sections of railroad track threatened by coastal erosion and landslides in San Clemente, moving forward with urgent work to ensure continued passenger and freight rail ...

Emergency action is necessary to address urgent threats from slope and beach erosion and to protect the community, rail passengers and overall rail operations. The work is projected to include approximately 95% sand and 5% rock reinforcement, known as riprap, only to be placed where needed to stabilize the slope and protect the track.

Emergency action is necessary to prevent additional disruption of vital rail service. In addition, continued erosion requires quick action to repair and replace existing riprap, and deliver enough sand to help protect the tracks.

Effort advances critical action to safeguard Southern California’s rail connection and public safety. ORANGE – The Orange County Transportation Authority Board of Directors on Monday authorized emergency actions to stabilize sections of railroad track threatened by coastal erosion and landslides in San Clemente, moving forward with urgent work to ensure continued passenger and freight rail ...

On April 12, OCTA authorized emergency actions to stabilize sections of railroad track threatened by coastal erosion and landslides in San Clemente, moving forward with urgent work to ensure continued passenger and freight rail operations through South Orange County.

The approximately six-week closure of Metrolink and Amtrak Pacific Surfliner train service is set to begin Monday, allowing crews to safely and efficiently conduct emergency repairs . ORANGE – Passenger rail service through San Clemente will be suspended beginning Monday, April 28, to allow for crews to safely conduct emergency construction aimed at stabilizing sections of track at immediate ...

The closure will allow OCTA to begin work under a partial emergency Coastal Development Permit granted by the California Coastal Commission that allows for riprap repair and sand placement north of Mariposa Point and removal of the remaining pedestrian bridge at Mariposa Point, which was damaged in a landslide last year that shuttered the rail ...

The approximately six-week closure of Metrolink and Amtrak Pacific Surfliner train service is set to begin Monday, allowing crews to safely and efficiently conduct emergency repairs . ORANGE – Passenger rail service through San Clemente will be suspended beginning Monday, April 28, to allow for crews to safely conduct emergency construction aimed at stabilizing sections of track at immediate ...

Crews are making progress in the ongoing emergency work to stabilize the coastal rail line in San Clemente. This work consists of removing the remaining spans of the San Clemente Beach Trail near Mariposa Point. Excavators were also positioned on the beach and inland side of the track to begin repairing and reinforcing the damaged riprap.

Passenger rail service through San Clemente was suspended beginning April 28 to allow for crews to safely conduct emergency work to reinforce sections of track at immediate risk from landslides and coastal erosion. The rail line is expected to be shut down for passenger service for a total of approximately six weeks, through early June.