Summary: This project added a carpool lane (approximately 2.5 miles) in both directions of I-5 between PCH and San Juan Creek Road in the cities of Dana Point, San Clemente, and San Juan Capistrano and reconstructed the on- and off-ramps at PCH/Camino Las Ramblas. Construction began on December 20, 2013, and was officially completed on July 3 ...
There is free shuttle bus service every 30 minutes both Saturday and Sunday from the San Juan Capistrano station to Dana Point Harbor. Shuttle meets passengers in front of The Vintage Steakhouse at the station.
Passenger Rail Service Temporarily Halted Through San Clemente to Allo… The action enables OCTA to protect the coastal rail line to preserve a critical transportation link for Southern California, the region and beyond.
A potential sand source location that is being evaluated by OCTA is Surfside Sunset, as well as other potential sand sources closer to the San Clemente placement sites. The current project schedule for dredging and sand placement is as follows:
"Company Name: PHILBIN CONSTRUCTION COMPANY, Contact: JOE PHILBIN, Address: 209 AVENIDA DEL MAR, SUITE 202, SAN CLEMENTE, CA 92672, Phone: (714) 9049860, Email: JOE@PHILBINCONSTRUCTION.COM","Gunite/Shotcrete Ditch Subcontractor, Pipe Supplier, Dewatering Subcontractor, Concrete Supplier, Cellular Confinement System Subcontractor and Supplier ...
While emergency work in San Clemente has been top priority, OCTA continues to work with local, state and federal partners to study and secure funding for lasting solutions ORANGE – While the Orange County Transportation Authority and Metrolink team continues emergency work to protect the rail line in San Clemente at Mariposa Point, OCTA is pushing ahead on a study to find lasting solutions ...
Removed landslide soil on rail side of wall layout line Cleared project site for reinstatement of rail service Debris cleared, wall in place and passenger service restored July 2023 Remove temporary barrier wall after City of San Clemente installs permanent solution
Crews are laying final, permanent striping, installing landscaping and closing out a few miscellaneous items on the segment, which is part of a $230 million project to extend the carpool lane in each direction from San Juan Capistrano to San Clemente and reconstruct the Avenida Pico interchange.
Mission Viejo to San Clemente via Rancho Viejo Rd / Camino Capistrano / El Camino Real
It will include a detailed analysis of seven miles of critical coastal rail corridor between Dana Point and San Clemente at the San Diego County line (map of study area on reverse).