The Orange County Transportation Authority (Authority) invites proposals from qualified consultants to provide Construction Management Services for the Placentia Metrolink Commuter Rail Station Project.
Meet Terms and Conditions of Emergency Authorization USACE Letter of Permission for sand placement to be submitted late Summer. CEQA – California Environmental Quality Act RGP – Regional General Permit eCDP – Emergency Coastal Development Permit USACE - United States Army Corps of Engineers
Consultant Services to Prepare Project Report & Environmental Document for the Northbound State Route 55 Improvement Project From Interstate 5 to State Route 91
Property Restoration Criteria: Biological Factors These restoration criteria represent the biological factors (those that relate directly to species/habitat issues and the impacts of the M2 freeway projects). Each criterion includes a brief definition to clarify any potential misunderstandings and guide evaluators.
Bike and E-Bike Ordinances
The conservation plan demonstrates that sufficient conservation is being provided to address the biological mitigation related to the freeway projects; an accompanying agreement streamlines the environmental permitting process and will help freeway projects reach completion faster.
Discussion As a result of the ongoing imminent threat to the rail line, on March 31, 2025, OCTA submitted an emergency Coastal Development Permit (eCDP) request to the California Coastal Commission, and a Regional General Permit 63 (RGP63) request to the United States Army Corps of Engineers (USACE).
In 2018, OCTA secured programmatic permits and assurances for federal and state clean water permitting requirements. Receipt of these permits represents the culmination of years of collaboration and support by the Board, environmental community, and regulatory agencies. To protect the Preserves in perpetuity, a non-wasting endowment was ...
The Coastal Rail Infrastructure Resiliency Project targets four locations within a 7-mile coastal section of the OCTA-owned Orange Subdivision. Work includes rock gradation installation, beach sand replenishment, and trail restoration.
비상 프로젝트는 해안 철도 복원력 연구와는 별개로 진행 중이며, 현재 진행 중입니다. 각 프로젝트 활동은 복잡성과 계약자 및 자재 수급 상황에 따라 다른 일정에 따라 진행됩니다. 자세한 내용은 자주 묻는 질문들 (FAQ) 를 포함한 1구역과 2구역에 대한 세부 정보. 이러한 긴급 프로젝트와 관련된 ...