I-605/Katella Avenue Interchange

Construction Updates

OCTA, in cooperation with Caltrans, is improving the local interchange at Interstate 605 and Katella Avenue to improve mobility, smooth traffic flow, and enhance pedestrian and bicycle facilities.

I-605 Katella Interchange logo with tagline Safer. Smarter. Smoother.     OCTA and OCGO Logo DarkBlue

Project Details

The I-605/Katella Avenue interchange connects the San Gabriel River Freeway, a major north-south transportation route in Orange and Los Angeles counties, with Katella Avenue, an east-west regional corridor.

The project will improve overall operations for vehicles, bicyclists and pedestrians by:

  • Modifying northbound and southbound ramps at Katella Avenue
  • Closing the gaps in existing bike lanes by adding Class II bike lanes along eastbound and westbound Katella Avenue
  • Enhancing sidewalk connectivity between Coyote Creek Channel and Epson Way
  • Constructing Americans with Disabilities Act (ADA) curb ramps and installing new signage and crosswalk pavement markings

details
Corridor City

Los Alamitos

Total estimated cost

$32 million

Schedule

Late June 2025 to Late 2026

Construction Activities

Construction is underway and generally occurs on weekdays. Crews are anticipated to perform the following daytime and nighttime activities listed below.

Nighttime activities are slated to begin following the Fourth of July holiday to minimize public impacts when lane reductions and ramp closures are required for crews to safely perform the work. These nighttime activities are expected to continue through the end of July. Check back soon for a list of specific ramp closures.

Daytime Work (6 a.m. to 4 p.m.)

  • Install construction signs
  • Remove vegetation
  • Relocate utilities

Nighttime Work (9 p.m. to 5 a.m.)

  • Install temporary concrete barriers to create a safe work zone
  • Restripe Katella Avenue, shifting traffic to the outside lanes
  • Demolish and reconstruct the center median on Katella Avenue/Willow Street beneath the freeway

This work may be loud. The schedule is subject to change due to inclement weather or unforeseen operational issues.


Rendering of Improvements along Katella Avenue

Project Map

The rendering above highlights planned improvements along Katella Avenue between Coyote Creek Channel and Epson Way. Key features include:

  • Reconfiguration of the northbound on- and off-ramps into a T-intersection
  • Addition of Class II bike lanes with hatched markings to indicate bike lane transitions
  • Installation of a new traffic signal at the northbound I-605/Katella Avenue off-ramp, along with upgraded signals at nearby intersections
  • Painted crosswalks and newly constructed sidewalks to enhance pedestrian access and safety

Community Outreach

As part of its comprehensive public awareness campaign, the Public Outreach team is offering opportunities for the community to learn more about the project, its benefits, construction activities, and potential impacts. These include:

  • Public webinars
  • Neighborhood meetings
  • Project briefings and presentations
  • Project booths at community events

The Outreach team is participating in the City of Los Alamitos’ Concerts in the Park on Thursday, July 17 from 6:30-8 p.m. at 4000 Farquhar Avenue. We encourage you to stop by to learn more and ask questions.

Construction Closures & Detours

Closures and detours for the I-605/Katella Avenue Interchange Project


Sign up to receive timely information about construction activities and upcoming closures and detours.

Social Media Feed

Latest Activity

Document Icon
.PDF
.PDF
June 27, 2025
Blue pdf icon
pdf
pdf
June 23, 2025
Blue pdf icon
pdf
pdf
June 13, 2025
Orange Video play icon
video
video
May 28, 2025
Document Icon
pdf

Contact the Outreach Team

If you have questions or would like to request information in another language, please contact the Outreach Team at 888-200-3302 or email 605KatellaInfo@octa.net.

Text "605Katella" to 888-720-7016 to receive text alerts.