  • Regional Capacity Program (Project O)

  • On August 10, 2020, the Orange County Transportation Authority’s (OCTA) Board of Directors (Board) authorized staff to issue calls for projects (call) for the Comprehensive Transportation Funding Program’s (CTFP) Regional Capacity Program (RCP) and Regional Traffic Signal Synchronization Program (RTSSP). The CTFP is the mechanism by which OCTA administers competitive funding for streets and roads projects. The 2021 Project O and Project P calls under Measure M2 (M2) closed on Thursday, October 22, 2020.

    Regional Capacity Program (Project O)

    Approximately $22 million in M2 funds will be available through the RCP for the Arterial Capacity Enhancement, Intersection Capacity Enhancement, and Freeway Arterial/Street Transition categories.

    For all construction projects awarded CTFP funds in excess of $500,000 and/or exceeding a 90-day construction period schedule, the local agency shall install and remove signage in accordance with OCTA specifications during the construction period. For signage specifications, click here.

    2021 CTFP Call Workshop

    OCTA held a workshop for interested applicants on Monday, August 31, 2020. Click here for the 2021 CTFP Call Presentation.

    The Questions and Answers from the Workshop are available here.

    CTFP Guidelines

    The Board approved revised CTFP Guidelines are available online and can be found here.

    OCFundTracker

    The OCFundtracker training manual can be downloaded here. Please contact OCTA staff if you require additional training on the database.

    Call Questions/Answers