Keeping Orange County Moving Today and Tomorrow

 

 

Early Action Plan in Place

 

To get things started, OCTA developed an Early Action Plan for Renewed Measure M. Under the plan, the following major freeway projects will be under way by 2012 to keep traffic flowing on these vital routes:

  • • Project D – Santa Ana Freeway (I-5) at Ortega Interchange. The City of San Juan Capistrano is advancing the environmental document and project report for this project.
    • Project G – SR-57 Northbound (NB) Orangethorpe to Lambert. A request for proposals was issued for the final design of this segment. The final design was split into two projects and two consultants were selected to start design.
    • Project G – SR-57 NB Katella to Lincoln. A request for proposals was issued and a consultant was selected for the preparation of the environmental document and project report for this project.
    • Project H – Westbound SR-91 from I-5 to SR-57. A request for proposals was issued and a consultant was selected for the preparation of the environmental document and project report for this project.
    • Project J – SR-91 from SR-55 to Foothill/Eastern Toll Road (SR-241) and eastbound from SR-241 to Corona Freeway (SR-71). The environmental document is under way for the new eastbound lane east of SR-241.
    • Project K – San Diego Freeway (I-405) from I-605 to SR-55. The Project Study Report is under way and the Environmental Analysis will be initiated in 2008.