Lakeview Ramp at SR-91 Reopens, Marking Last Major Construction Activity

Construction crews reopened the eastbound Lakeview on-ramp to make commuting easier for those traveling along the Riverside Freeway (SR-91).

The reopening of the ramp marks the completion of ramp reconstruction and realignment operations on the SR-91 Westbound and Eastbound Lane Addition Project.

 This $75-million freeway improvement project adds 12 lane miles to a pivotal stretch of the SR-91 between the Costa Mesa Freeway (SR-55) and Eastern Toll Road (SR-241).

Crews successfully finished reconstructing and realigning a total of 15 on- and off-ramps and opened 12 lane miles to peak hour traffic last year. As a result, the project is now on track to be completed within the first quarter of 2013.

Until then, construction crews will finalize lane striping in both the west and eastbound directions as well as working on completing a 1.5-mile soundwall, a maintenance road and other operational tasks.

This project is funded by Orange County’s Measure M program as well as state transportation dollars. Caltrans District 12 and SEMA Construction also collaborated on this project with OCTA.

Back to News Releases

Meet the Team

Joel Zlotnik

Communications Manager
(714) 560-5713

Adam Raley

Communications Specialist, Principal
(714) 560-5510

Media Contacts

Eric Carpenter

Communications Specialist, Senior
(714) 560-5697

Megan Abba

Communications Specialist, Senior
(714) 560-5671

Resources

Get Connected

Sign up to receive OCTA press releases straight to your email.

OCTA Media Team on Twitter
Media Resources

Stock photos and logos, and links to annual reports, board agendas and more.

About

The Orange County Transportation Authority’s Public Information Office responds to media inquiries, issues press releases and provides information about OCTA to the public and stakeholders.