View a Renewed M Project
Image Gallery
In January 2008, OCTA completed the Euclid Street Signal
Synchronization Project that optimized signal timing along a 16-mile
segment of Euclid Street. Travel times along Euclid Street were
improved between 16 and 24 percent with the new timings.

A
second synchronization project at OCTA along a nine-mile segment of Oso
Parkway/Pacific Park Drive is currently under way. Optimized timing has
been implemented in conjunction with strategic signal system upgrades
and a monitoring effort. Studies show that travel times along Oso
Parkway/Pacific Park Drive were improved between 20 and 31 percent.
In April 2008, the California Transportation
Commission (CTC) awarded OCTA $4 million as part of the Proposition 1B
Traffic Signal Synchronization Program. This, combined with $4 million
from Measure M, will provide $8 million to fund signal synchronization
along ten significant street corridors comprised of 533 signalized
intersections over the next three years. OCTA has developed a schedule
to fund and implement these projects and will start the first set of
these projects in January 2009.
Finally, OCTA began developing a master plan for the Regional
Traffic Signal Synchronization Program. The $450 million program is
funded by Renewed Measure M. The goal of the program is to improve the
flow of traffic by developing and implementing regional signal
coordination through more than 2,000 intersections. The master plan
effort will be complete in fall 2009.
OCTA Staff: Anup Kulkarni (714) 560-5867

In January 2008, OCTA completed the Euclid Street signal
synchronization project that implemented optimized signal timing along
a 16-mile segment of Euclid Street. Travel times along Euclid Street
were improved between 16 and 24 percent with the new timings.
A second OCTA synchronization project along an 8¾ mile segment of
Oso Parkway/Pacific Park Drive will be completed in fall
2008. Optimized timing has been implemented in conjunction with
strategic signal system upgrades and a monitoring effort. Travel times
along Oso Parkway were improved between 13 and 27 percent with the new
timings.
In April 2008, the California Transportation Commission awarded OCTA
$4 million as part of the Proposition 1B Traffic Signal Synchronization
Program for signal synchronization. Combined with $4 million from
Measure M this will provide $8 million to fund signal synchronization
efforts along ten significant street corridors comprised of 533
signalized intersections over the next three years. OCTA has developed
a schedule to fund and implement these projects and will start the
first set of these projects in January 2009.
Finally, OCTA began work to develop a master plan for the Regional
Traffic Signal Synchronization Program. The $450 million (plus 20
percent local match) program is funded by M2. The goal of the program
is to improve the flow of traffic by developing and implementing
regional signal coordination through more than 2,000 intersections.
The master plan effort will be complete in fall 2009.
OCTA Staff: Anup Kulkarni (714) 560-5867

In January 2008, OCTA completed the Euclid Street Signal
Synchronization Project that implemented optimized signal timing along
a 16-mile segment of Euclid Street. Travel times along Euclid Street
were improved between 16 and 24 percent with the new timings.
In December 2008, a second synchronization project along an 8¾-mile
segment of Oso Parkway/Pacific Park Drive was completed. Optimized
timing has been implemented in conjunction with strategic signal
systems upgrades and a monitoring effort. Travel times along Oso
Parkway were improved between 13 and 27 percent with the new timings.
In April 2008, the California Transportation Commission awarded OCTA
$4 million as part of the Proposition 1B traffic signal synchronization
program. This, combined with
$4 million from M1, will provide $8 million to fund signal
synchronization along 10 significant street corridors comprised of 533
signalized intersections over the next three years. OCTA has developed
a schedule to fund and implement these projects and will start the
first set of these projects in April 2009 pending expected release of
the funds from the State of California.
Finally, OCTA has been working on a master plan for the regional
traffic signal synchronization program. The $450 million (plus 20
percent local match) program is funded by M2. The goal of this program
is to improve the flow of traffic by developing and implementing
regional signal coordination through more than 2,000 intersections.
The master plan effort will be complete in fall 2009.
The OCTA Board approved a request from the City of Laguna Niguel for
$3.8 million in additional funding to complete the final segment of the
Moulton Parkway Smart Street Project. Included in the original Measure
M, the goal of the Smart Street Program is to improve travel time and
traffic flow by constructing high-capacity, high-volume corridors along
Beach Blvd., Katella Ave., Imperial Hwy., and Moulton Pkwy.
OCTA has submitted a list of ten projects to compete for $100 million in Proposit
ion
1B funds which will be made available under the Traffic Light
Synchronization Program. The purpose of the program is to provide
funding to be used for traffic light synchronization and other
technologies to improve the effective capacity of local streets and
roads. If the list of projects is approved, it would result in an
additional 158 miles of synchronized corridors within Orange County.
Over $100,000 in Commuter Urban Rail Endowment (CURE) funding was made
available
in order to make final revisions to the design of a pedestrian
undercrossing planned for the Orange Transportation Center.
Constructing a pedestrian underpass will improve safety and provide
easier access from the parking lot to the station platform and bus
transfer facilities. With the design phase completed, construction on
the project is scheduled to begin in April 2008. Click here for more
information on the project.
OCTA Staff: Anup Kulkarni (714) 560-5867
In January 2008, OCTA completed the Euclid Street signal synchronization project that implemented optimized signal timing along a 16-mile segment of Euclid Street. Travel times along Euclid Street were improved between 16 and 24 percent with the new timings.
A second OCTA synchronization project along an 8¾ mile segment of Oso Parkway/Pacific Park Drive will be completed in fall 2008. Optimized timing has been implemented in conjunction with strategic signal system upgrades and a monitoring effort. Travel times along Oso Parkway were improved between 13 and 27 percent with the new timings.
In April 2008, the California Transportation Commission awarded OCTA $4 million as part of the Proposition 1B Traffic Signal Synchronization Program for signal synchronization. Combined with $4 million from Measure M this will provide $8 million to fund signal synchronization efforts along ten significant street corridors comprised of 533 signalized intersections over the next three years. OCTA has developed a schedule to fund and implement these projects and will start the first set of these projects in January 2009.
Finally, OCTA began work to develop a master plan for the Regional Traffic Signal Synchronization Program. The $450 million (plus 20 percent local match) program is funded by M2. The goal of the program is to improve the flow of traffic by developing and implementing regional signal coordination through more than 2,000 intersections. The master plan effort will be complete in fall 2009.
In April 2008, the California
Transportation Commission (CTC) awarded OCTA $4
million as part of the Proposition 1B traffic signal synchronization program
for signal synchronization. This combined with $4 million from the original
Measure M (M1) will provide $8 million to fund signal synchronization along 10
significant street corridors comprised of 533 signalized intersections over the
next three years. OCTA has developed a schedule to fund and implement these
projects and will start the first set of these projects in July 2009.
Lastly, OCTA has been working on
a master plan for the regional traffic signal synchronization program. The $450
million (plus 20 percent local match) program is funded by M2. The goal of the
program is to improve the flow of traffic by developing and implementing
regional signal coordination through more than 2,000 intersections. The master
plan effort will be complete in fall 2009.
Anup Kulkarni (714) 560-5867
Street Maintenance and Improvements
When Renewed Measure M (M2) begins in 2011, more than 7,200 miles of Orange County’s aging roadways will be maintained by the measure’s revenues. Thirty-two percent of M2’s net revenues will be allocated to maintain streets, fix potholes, improve intersections, and widen city streets and county roads.
Countywide Signal Synchronization
M2 will improve the existing system of streets by implementing a countywide signal synchronization program. OCTA, along with local agencies within Orange County, will collaborate on the project and synchronize lights along major streets to reduce stop-and-go travel and increase the flow of traffic.
In 2007, OCTA completed synchronization pilot projects along Euclid Street and Oso Parkway / Pacific Park Drive, both were successful and offer promising results for future streets.
Roads in Your Community
Renewed Measure M will maintain and improve Orange County’s roadways and provide safer and faster travel solutions to commuters.