Project Schedule and Upcoming Construction

Southbound I-405 / Eastbound SR-22 Connector Bridge Demolition | Mid- to Late-Summer 2013

WHAT:
The southbound I-405 connector to the eastbound SR-22 freeway is being reconstructed in order to make room for the new SR-22 / I-405 carpool connector. Once construction on the new connector is complete, the old connector must be demolished. Since the southbound I-405 / eastbound SR-22 connector crosses over the I-405 freeway (near Valley View Street), in order to demolish the old structure, portions of the eastbound SR-22, northbound I-405 and southbound I-405 freeways will be closed for approximately 20 hours, over a weekend in mid- to late-summer 2013.. 

WHEN
Portions of the eastbound SR-22, northbound I-405 and southbound I-405 freeways will be closed from approximately 9 p.m. on  a Saturday to approximately 5 p.m. on  a Sunday.  Please be advised these dates and times are subject to change due to unforeseen operational factors or inclement weather.

What will be closed?

  • Northbound I-405 freeway will be closed at Valley View St.
  • Southbound I-405 freeway will be closed at the I-605 freeway junction
  • 7th St.  / Eastbound SR-22 will be closed at southbound I-405 freeway junction

Recommended Detours
In order to bypass the area while the southbound I-405 / eastbound SR-22 is being demolished, the following recommended detour routes are available.

From Northbound I-405 use one of the following (outlined in BLUE):

  • Exit Beach Blvd. turn right; Take WB SR-22 to reconnect with NB I-405
  • Exit Westminster Ave. (EAST) turn left; Right on Bolsa Chica Rd.; Take WB SR-22 to NB I-405
  • Exit Valley View St., left on Garden Grove Blvd.; Right on Valley View St.; Take WB SR-22 to NB I-405 

From Southbound I-405 use one of the following (outlined in GREEN):

  • Exit Studebaker Rd. turn right; Left on E. 2nd St. / Westminster Ave.; Continue on Westminster Ave. to access SB I-405
  • Merge onto NB I-605; Exit Katella Ave. turn right; Right on Valley View St. to access SB I-405

From Southbound I-605 use the following detour (outlined in GREEN):

  • Exit Willow St. turn right; Left on Studebaker Rd.; Left on E. 2nd St. / Westminster Ave.; Continue on Westminster Ave. to access SB I-405

From 7th St. / Eastbound SR-22 use the following (outlined in GREEN):

  • Merge onto NB I-605; Exit Katella Ave. turn right; Right on Valley View St. to access SB I-405

Other Related Closures:
Traffic will be shifted onto the new southbound I-405 / eastbound SR-22 connector one week before the old connector is demolished. In order to restripe the freeway and shift traffic onto the new connector, crews must close the existing southbound I-405 / eastbound SR-22 connector for 55 hours. This 55-hour closure will take place from 10 p.m. on a Friday to 5 a.m. the following Monday, in mid- to late-2013. More detailed information will be available as the date nears.

Eastbound SR-22 / Northbound I-405 Connector | 12-Month Closure
CONNECTOR CLOSED AS OF SUNDAY, SEPTEMBER 16, 2012  

The eastbound SR-22 connector to the northbound I-405 freeway is scheduled to close for approximately 12 months beginning on Sunday, September 16 at 11 p.m. This connector must be reconstructed in order to accommodate the new I-405 / I-605 carpool connector.

Recommended Detour (from the eastbound SR-22 freeway)

  • From the eastbound SR-22, exit Studebaker Road, turn right and proceed north on Studebaker Road to access the northbound I-405 freeway on-ramp

 

Eastbound SR-22 to Northbound I-405 Connector Closure Detour Map

 

Seal Beach Boulevard Bridge Reconstruction
The Seal Beach Boulevard bridge over the I-405 freeway has been reduced to one lane in each direction, with a center median dedicated solely to emergency services vehicles. This configuration will remain in place for approximately 11 months.
In mid-2013 the bridge will be restored to two lanes in each direction until the new structure is completed in mid-2014. The final bridge will have four northbound lanes and three southbound lanes, essentially doubling the size of the original structure.

Lane Reduction Map

Seal Beach Boulevard Pedestrian Detour Map

Seal Beach Boulevard Alternate Routes Map

Seal Beach Blvd. Alternate Route


DISCLAIMER: Please be advised these dates and times are subject to change due to unforeseen operational factors or inclement weather.